Hershey Road and College Avenue
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Street
|
From
|
To
|
Tentative Work Start Date
|
Anticipated Resurface Date
|
|
St Joseph Dr
|
Eastland Dr
|
Washington St
|
10/19/2009
|
Done 11/4
|
|
Eastland Dr
|
St Joseph Dr
|
Fairway Dr
|
10/19/2009
|
Done 11/6
|
|
White Oak Rd
|
Locust St
|
Market St
|
7/2/2009
|
Done 7/17 |
|
IAA Dr
|
Kmart Crossing
|
Empire St
|
10/19/2009
|
Done 11/9 |
The schedule of streets to have strip milling of bad joints and asphalt inlays in 2009 are:
|
Street
|
From
|
To
|
Tentative Work Start Date
|
Anticipated Inlay Date
|
|
Twin Lake Rd
|
Fallen Oak Rd
|
Lake Bluff Rd
|
9/11/2009
|
Done 10/20/2009 |
|
Hidden Lake Dr
|
Lake Fork Rd
|
Twin Lake Rd
|
9/11/2009
|
Done 10/20/2009 |
|
Fallen Oak
|
Lake Fork Rd
|
Twin Lake Rd
|
9/11/2009
|
Done 10/20/2009 |
| Chicory Ln | Wildflower Pl | Goldenrod Rd |
9/11/2009
|
Done 10/19/2009 |
| Bittersweet Cir | Goldenrod Rd | Clover Ct |
9/11/2009
|
Done 10/20/2009 |
|
Commerce Pkwy
|
Veterans Pkwy
|
Hamilton Rd
|
10/2/2009
|
Done 10/14/2009
|
|
Hamilton Rd
|
Morrissey Dr
|
Commerce Pkwy
|
10/2/2009
|
Done 10/14/2009
|
|
Colton Ave
|
Empire St
|
Locust St
|
10/19/2009
|
Done 10/19/2009
|
The schedule of streets to be patched by a contractor in 2009 are:
|
Street
|
From
|
To
|
Tentative Work Start Date
|
Anticipated Finish Date
|
|
Arrowhead Dr
|
Eastport Dr
|
Challis Dr
|
8/17/2009
|
Done 8/20
|
| College Ave | Hershey Rd | North Pointe Dr |
8/31/2009
|
Done 9/2 |
|
Fairway Dr
|
Empire St
|
Robinhood Ln
|
8/17/2009
|
Done 8/19 |
| Fell Ave | Emerson St | Beecher St |
8/17/2009
|
Done 8/19 |
| Fox Creek Rd | Danbury Dr | Bridge |
8/17/2009
|
Done 8/19 |
|
Lee St
|
Graham St
|
Union St
|
8/17/2009
|
Done 8/19
|
|
Mercer Ave
|
Herbert
|
Lincoln St
|
9/8/2009
|
Done 9/14 |
|
Market St
|
Lee St
|
Roosevelt Ave
|
8/17/2009
|
Done 8/19 |
| Oakland Ave | Euclid Ave | Weldon St |
8/17/2009
|
Done 8/19 |
|
Washington St
|
Morris Ave
|
Western Ave
|
8/17/2009
|
Done 8/20 |
|
Washington St
|
State St
|
east
|
8/17/2009
|
Done 8/19 |
| Wisteria Ln | Airport Rd | Hackberry |
8/17/2009
|
Done 8/20 |
| Woodfield Rd | College Ave | Northwood Ln |
8/17/2009
|
Done 8/20 |
| Woodrig Rd | Main St | Geneva Blvd |
9/16/2009
|
Done 9/21 |
The schedule of alleys to be resurfaced in 2009 are:
|
Alley
|
From
|
To
|
Tentative Work Start Date
|
Anticipated Resurface Date
|
|
East of White Pl
|
Empire St
|
Emerson St
|
8/19/2009
|
Done 8/26
|
|
North of Jefferson St
|
Clinton St
|
Clayton St
|
8/19/2009
|
Done 8/25
|
The schedule of roads to be repaired then oiled and chipped in 2009 are:
|
Street
|
From
|
To
|
Tentative Work Start Date
|
Anticipated Finish Date
|
|
Lutz Rd
|
Morris Ave
|
Luther Oaks Ent.
|
8/17/2009
|
Done 9/2
|
|
Bloomingtondale Rd
|
Six Points Rd
|
south
|
8/17/2009
|
Done 9/2
|
Construction and project layout began on September 3, 2008. Lincoln Street was opened and the Traffic Signals began operation on October 13, 2009.
The improvements included construction of new pavement to connect the two sections of Lincoln Street and installation of traffic signals at the Morrissey (US 150) & Lincoln intersection. Sanitary sewer and water main was installed to service area residents.
The Ramp Replacement Program is used to upgrade existing intersection sidewalk ramps to current standards. To request that the ramps be upgraded at a certain location, call 434-2225.
|
|
|
|
|||||||||